Answer: One full day Explanation: For a 9’ x 9’ bathroom with a standard tile pattern, a professional installer typically needs:
• Subfloor prep
• Tile layout and installation
• Cutting and setting tiles
Grouting is often done later the same day or the next day, but the tile installation itself usually fits into one full workday. |
| SD REMODELING & RESTORATIONS |
Answer: 2-4 hours Explanation: Day 1: Demo (if needed) and floor prep—making sure the subfloor is solid, level, and clean. We’ll also lay out the tile pattern and start setting the tiles.
Day 2: Finish laying tile and let the thinset cure properly (usually overnight).
Day 3: Grout the floor, clean up, and allow everything to set.
It could take a little longer if the layout is tricky, the floor needs repair, or there's a lot of cutting around fixtures. But under normal conditions, we’re in and out in about 3 days. |
| Grellis Construction |
Answer: 4-8 hours Explanation: That is a small space so I would use a quick set mortar. I can install that area in two hours. Drying time of two hours and then grout and dry time of two hours. Depending on floor condition before starting. |
| KRAOS LLC |
|
| ProMatcher |
Answer: Three full days Explanation: 2-3 Days |
| Ace Handyman Services Lake Norman |
Answer: One full day Explanation: A skilled installer would typically take around one day to install the tile floor, including prep time, laying the tiles, and grouting. |
| CDH Artisans |
Answer: Two full days Explanation: Provided the floor is already bare and we don’t have much prep work, Ceramic tile is a 2 to 3 day process always. Installation on first day and if it’s a small job we can even grout it the first day but to seal always requires a curing process and an additional day |
| Apache Restoration and Design |
|
| ProMatcher |
Answer: One full day Explanation: But that depends on the type of grout and adhesive you use for the tile. |
| Jack of trades services |
Answer: One full day Explanation: Assuming the surface is ready for tile, the tile can be installed in one day. A second short day is also required to grout and seal as needed. |
| Rafael Tile Works |
Answer: 4-8 hours Explanation: to ensure that everything lines up correctly and that every tile is level and plain would average 4 to 8 hours. Site condition plays a big role. |
| PTR UNLIMITED LLC |
|
| ProMatcher |
Answer: Two full days Explanation: Depending on existing flooring, if covered with tile removal with roto hammer, clean up floor to accept new Hardie backer, tile it. let it set, grout, clean up, |
| DLR Construction and Investment LLC |
Answer: One full day Explanation: Depending on the preparation |
| M&D Home Improvement |
Answer: 2-4 hours Explanation: To lay the tile only takes a couple hours. But from beginning to end, it can be done in a day |
| Number one choice LLC |
|
| ProMatcher |
Answer: 8-12 hours Explanation: Barring all unforseen situations arriving, being just the tile labor without including tear out, repair, prep, backer board, removing fixtures, replacing fixtures, trim and such, its feasible to assume the time could be paid in a 8 hour day and upon curing of the thinset, grouted the following day in half a days time. |
| brown remodeling and construction |
Answer: 4-8 hours Explanation: Depending on slab condition and layout |
| Smith's services |
Answer: 4-8 hours Explanation: If you know what your doing. |
| Handy Man Services |
|
| ProMatcher |
Answer: Two full days Explanation: One day for installing and second day for grout. |
| Splash of colors painting |
Answer: One full day Explanation: It would take couple hours to install tile. Then would have to wait 24 hours for grouting process. So one day total instal time from begining to completed |
| Brock's handyman |
Answer: Two full days Explanation: One day for installing and second day for grout. |
| LNMC ENTERPRISE, LLC |
|
| ProMatcher |
Answer: One full day Explanation: In order for it to be done right you don't rush thru a job take your time and make it look professional |
| Southern Handyman Services & More |
Answer: 2-4 hours Explanation: for me some guys take two days |
| TAC Tile |
Answer: Two full days Explanation: you have to make a layout and need 2 days to complete |
| AMG Flooring & Paint, Inc. |
|
| ProMatcher |
Answer: 4-8 hours Explanation: It really all depends on the set up the type of tile but usually we can get the tile down 48 hours and come back the next day and throughout it and let it set and there you are brand new bathroom floor |
| MRG Painting & Projects |
Answer: 4-8 hours Explanation: With tear out and installation of Hardi backer. It should take 4-8 hrs. Usually leveling is involved with older homes. |
| Bath Makeover Pro LLC |
Answer: One full day Explanation: Proper preparation is the key. |
| R.N. Home Improvement and Repair Co. |
|
| ProMatcher |
Answer: 4-8 hours Explanation: Well given that the underlayment is in good condition and is solid. Also, given that any old tile that may be being replaced does not require significant effort to remove, 4 to 8 hours would be an appropriate amount of time. Furthermore, we have found in many cases that the underlayment is not significant enough to protect from cracking especially in cases where there is significant weight. There are a lot of factors that can go into laying a new tile floor. However in a perfect situation 4-8 hours would be reasonable. |
| Price is Right Painting and Remodeling |
Answer: One full day Explanation: Depends on layout and size of tile. |
| M.G Tile & Marble Inc. |
Answer: 4-8 hours Explanation: An experienced tile setter can set a 9x9 room in 4-8 hours with a return trip for grouting and clean-up. |
| Penn Builders & Installations Co, Inc |
|
| ProMatcher |
Answer: Two full days Explanation: glue needs 24 to set before you can grout between tiles. so you will need 2 full days to complete the job. |
| snssolutions |
Answer: 8-12 hours Explanation: 6-8 hours to set tile let stand overnight then grout tile and clean |
| Hands With A Mission |
Answer: Two full days Explanation: First day to do existing flooring removal, install subflooring and tile. Second day to grout. |
| Construct Boss |
|
| ProMatcher |
Answer: 4-8 hours Explanation: All will depend on the amount of fixtures that are in the way and what needs to be uninstalled to facilitate a new floor |
| iDesign Interiors, LLC |
Answer: 8-12 hours Explanation: The flooring has to be leveled and smooth before tile can be laied and it is time consuming. |
| G&J Carpentery Services |
Answer: 4-8 hours Explanation: Many variables |
| ARTIZTEK TILE DESIGNS |
|
| ProMatcher |
Answer: 8-12 hours Explanation: Basic labor to install ceramic floor tile with favorable site conditions. Layout tile pattern. Fabricate and install with thinset mortar. Grout and clean surface. Includes planning, equipment and material acquisition, area preparation and protection, setup and cleanup. |
| Arcadian Handyman |
Answer: One full day Explanation: Typically needs a revisit the next day for grouting and sealing. |
| Pinchot Home Improvement LLC |
Answer: 8-12 hours Explanation: The correct way to install a tile floor is to install cement board first. Once the cement board is done then you can tile. Let the tile setup over night and grout the next day. |
| Ward Kitchen & Bath |
|
| ProMatcher |
Answer: 8-12 hours Explanation: Basically one day maybe another four hours because you have extra prep or subfloor to put down toilets to pull or vanities to replace so it all varies just for tile 8 hours come back and grout it in the morning |
| Foster Construction |
Answer: 2-4 hours Explanation: Half fau gor small bath |
| Texmaxx Construction L.L.C. |
Answer: 2-4 hours Explanation: Standard pattern is the easiest pattern for tile installers. Definitely no more than 4 hours for proper installation in a 9'x9' room. |
| Your buddy at the beach LLC |
|
| ProMatcher |
Answer: 4-8 hours Explanation: It depends on cuts and the type of sub-floor |
| GetGreatFlooring.com |
Answer: 4-8 hours Explanation: After installing let dry good before walking or moving heavy furniture on it. |
| Saul Reyes Contracting. |
Answer: One full day Explanation: We're efficient and if you're bathroom is standard sized it'll take us a day to install the tiles and maybe 1 to 2 hours for the grout. |
| The Raystruction Group LLC |
|
| ProMatcher |
Answer: 8-12 hours Explanation: Lay tile, then grout next day |
| Midwest construction |
Answer: 8-12 hours Explanation: Take little more time let dry tinsel and then we can apply ground to make a perfect job. |
| Professinal Plumbing & Handyman |
Answer: 4-8 hours Explanation: if everything is good there should be no problem |
| Dmar.Remodeling.llc |
|
| ProMatcher |
Answer: Three full days Explanation: first day prep-work (hardie backer) and start laying tile. Second day finish installation. third day install grout and drying process . |
| Russ Construction & Remodeling LLC |
Answer: 2-4 hours Explanation: Pretty basic . unless there are boarders and inlays |
| 1964 |
Answer: Two full days Explanation: you set the tile in one day then you go back the next day to grout |
| Four All Seasons Construction |
|
| ProMatcher |
Answer: 4-8 hours Explanation: We are professional tile layers with years of experience. We lay tile on a daily basis. |
| Seacrest Renovations |
Answer: 4-8 hours Explanation: It can take anywhere from 3 to 7 hours to lay a typical ceramic tile floor, I chose 4-8 hours because while being time efficient it is never our policy to rush. |
| BSH Home Design |
Answer: One full day Explanation: It can take more, or less time depending on the existing conditions |
| Bradley Paint & Remodeling |
|
| ProMatcher |
Answer: 4-8 hours Explanation: Standing up on the work needs to be done, job can take a little bit longer of subfloor needs to be installed! If not Needed floor can be installed within 2 hours. |
| Colorful Homes Painting And Restoration |
Answer: 2-4 hours Explanation: If the tiles are large than it can be done quickly. If they are small to tiny than it can take forever. |
| Kitchen Remodeling Chicago |
Answer: Two full days Explanation: a day to prep, set the tile, and let it cure, and another day to grout and clean and for it to cure |
| A Better Flooring |
|
| ProMatcher |
Answer: Two full days Explanation: We do all the prepping and installation on day one. Then we can grout the day after. All cuts can be done during installation since the floor is small enough. |
| Contractor Plus inc. |
Answer: 4-8 hours Explanation: Depending on the pattern and design. |
| DC Construction Services Inc. |
Answer: 4-8 hours Explanation: The install of the tile is fairly quick, but you do have to wait for the thin set to dry prior to grouting. |
| Future Roofing & Construction LLC |
|
| ProMatcher |
Answer: Two full days Explanation: The question leaves a lot of scenarios to the professional answering this question, we would remove existing vanities and cabinets, toilet demo existing floor-make any necessary subfloor corrections or repairs, lay tile underlayment then lay tile, grout tile, clean up then reinstall or install new vanity with top and fixture, toilet etc... |
| Nu-Face of PA |
Answer: 4-8 hours Explanation: This is after the Durarock is secured. |
| Chris Benedict's All Trades Service |
Answer: 8-12 hours Explanation: Lay the tile. Wait at least 24 hours for adhesive to set/cure. Come back in and grout, polish immediately. Enjoyment ready in 6-8 hours. |
| LIFETIME WARRANTY CONSTRUCTION |
|
| ProMatcher |
Answer: One full day Explanation: Using quick set thin-set. A floor this size can be laid down and grouted in one day. |
| Freedom Handyman Services, Inc. |
Answer: Two full days Explanation: It really depends on the pattern chosen and the cuts required. Once the floor is prepped and laid out, it takes very little time to actually set the tiles in place. Then you have to wait until they set (24 hours) before you can grout them and trim out the rest of the floor. |
| Handyman Matters North Houston |
Answer: 8-12 hours Explanation: The tile glue has to set and dry to enable the grouting. |
| ARCHIQUEST, INC |
|
| ProMatcher |
Answer: 2-4 hours Explanation: With a standard pattern it should only take a couple of hours to lay the tile but you have to come back the following day to grout! |
| A Diamond Affair Interiors |